A Kazakh oil project that is $30 billion over budget, with no oil produced years after the project was started in 2005, is an example of what western oil companies can run into when tackling complex projects with many partners. It also shows why oil is becoming more costly to produce, keeping upward pressure on oil prices. The project is already costing western oil companies over $50 billion. This includes Italy's Eni, Shell, Total SA, ConocoPhillips, and Exxon. The project started in 2005 with collaboration between the state oil company LMG and the western companies led first by Exxon, and then as a compromise by Eni. Part of the problem is the requiredment of the Kazakh government to hire local employees who lack the necessary experience. The gas from wells has 17% hydrogen sulfide and it took 2 years to adapt infrastructure to this type of well. Housing for staff delayed the project for a year. In 2008 a target date of 2013 was set. In 2013 the project was stopped because of pipeline leaks which have still not been fixed. Causes relate to defects in pipe and in the way the pipe deteriorates in contact with the hydrogen sulfide. Kazakh government officials have responded to the delays by adding fines for the western oil companies, including a $735 million fine related to the pipe failure and gas burning. This may have reduced the motivation of the oil companies to give priority to tackling the issues. On the Kazakh side the problem is seen as being on the outside and lacking participation in the management of the complex project....